FINALTERM EXAMINATION
Spring 2009
MGMT627 Project Management

Marks: 81

Question No: 1 ( Marks: 1 ) - Please choose one
Project management specialists frequently distinguish between weak and strong matrix
structures. Identify the chief characteristic of a weak matrix.
  • Team members are not fully trained to do the job
  • The functional manager has relatively more influence in making decisions than the project manager
  • Management reserve is rapidly being depleted
  • Re-baselining occurs frequently

Question No: 2 ( Marks: 1 ) - Please choose one
High production costs are typically found at which of the following Project Life Cycle
(PLC) phases?
  • Maturity phase of the PLC
  • Growth phase of the PLC
  • Decline phase of the PLC
  • Introduction phase of the PLC

Question No: 3 ( Marks: 1 ) - Please choose one
Which of the following is included in Project Scope Management?
  • Plan development
  • Project plan execution
  • Integrated change control
  • Initiation

Question No: 4 ( Marks: 1 ) - Please choose one
Which of the following statements is TRUE about scope management
?
  • It entails managing the project's work content
  • It is a subset of configuration management and as such is performed by scope management specialists
  • It is concerned with defining and controlling what is or is not included in the project
  • It is not a concern of the project manager

Question No: 5 ( Marks: 1 ) - Please choose one
Which of the following statements best describes the project life-cycle?
  • Project concept, project execution, and project reporting
  • Project planning, work authorization, and project reporting
  • Project planning, project control, project definition, work breakdown structure development and project termination
  • Project concept, project planning, project execution, and project close-out

Question No: 6 ( Marks: 1 ) - Please choose one
All of the following are activities of the Project Engineering Manager, EXCEPT:
  • Process flow sheets
  • Equipment data specifications
  • Process liaison
  • Bid analysis

Question No: 7 ( Marks: 1 ) - Please choose one
Which of the following shows the impact on results of changes in assumptions?
  • Controlled variation
  • Scenario analysis
  • Financial package blueprint
  • Feasibility analysis

Question No: 8 ( Marks: 1 ) - Please choose one
All of the following factors affect the estimation decision, EXCEPT:
  • Size of project
  • Size of team
  • Past experience
  • Length of schedule

Question No: 9 ( Marks: 1 ) - Please choose one
Which of the following is NOT a formal method of Selecting Projects?
  • The Sacred Cow
  • The Operating Necessity
  • The Competitive Necessity
  • Comparative Benefit Model

Question No: 10 ( Marks: 1 ) - Please choose one
The success of a project depends critically upon which of the following?
  • Effort
  • Care
  • Skill
  • All of the given options

Question No: 11 ( Marks: 1 ) - Please choose one
Which of the following is NOT an input to project plan execution?
  • Work authorization system
  • Project plan
  • Corrective action
  • Preventive action

Question No: 12 ( Marks: 1 ) - Please choose one
Which of the following spells out clearly defined and agreed-upon goals in beginning of
project?
  • Project Mission
  • Project Schedule
  • Project Execution Plan
  • Project Scope

Question No: 13 ( Marks: 1 ) - Please choose one
All of the following are included in the Functional Level Planning, EXCEPT:
  • Coordination of work activities
  • Commitment to group goals
  • Vertical & lateral communication
  • Lateral communication

Question No: 14 ( Marks: 1 ) - Please choose one
All of the following are external economic variables for strategic planning in the tire
industry, EXCEPT:
  • Forecast of industry
  • Division of market
  • Competition
  • Steel and chemical output
Question No: 15 ( Marks: 1 ) - Please choose one
Who among the follolwing is responsible to provide technical directions to any problem?
  • Assistant project manager
  • Program manager
  • Line manager
  • Project manager

Question No: 16 ( Marks: 1 ) - Please choose one
Which of the following types of managers is the true technical expert?
  • Program manager
  • Line manager
  • Project manager
  • Assistant project manager

Question No: 17 ( Marks: 1 ) - Please choose one
Which of the following defines the size of the project?
  • Project plan
  • Project scope
  • Project charter
  • Work breakdown structure

Question No: 18 ( Marks: 1 ) - Please choose one
Which of the following is prepared before project approval?
  • Project scope document
  • Project charter
  • Business case
  • Project scope statement

Question No: 19 ( Marks: 1 ) - Please choose one
In scope verification process, who will give the formal acceptance of work completion?
  • Top management
  • Customers
  • Stake holders
  • Project manager

Question No: 20 ( Marks: 1 ) - Please choose one
Which of the following is the cause of scope creep?
  • Cost reduction
  • Cost overrun
  • Cost allocation
  • Cost maintenance

Question No: 21 ( Marks: 1 ) - Please choose one
How is the earliest time denoted?
  • TL
  • TE
  • ET
  • LT

Question No: 22 ( Marks: 1 ) - Please choose one
The earliest and latest times, are which of the following?
  • Dependent variables
  • Random variables
  • Independent variables
  • Fixed values

Question No: 23 ( Marks: 1 ) - Please choose one
An event, represents which of the following?
  • Beginning of an activity
  • Ending of an activity
  • Beginning or ending of an activity
  • Duration of an activity

Question No: 24 ( Marks: 1 ) - Please choose one
In CPM, which of the following in each activity is/are considered?
  • Time
  • Performance
  • Cost and performance
  • Time and cost

Question No: 25 ( Marks: 1 ) - Please choose one
Printers and plotters, prefer to draw which of the following?
  • Circle
  • Square
  • Dotted line
  • Straight line

Question No: 26 ( Marks: 1 ) - Please choose one
In precedence diagram, what does dotted line indicates?
  • Event
  • Relationship
  • Slack
  • Critical path

Question No: 27 ( Marks: 1 ) - Please choose one
Who among the following is responsible for the development of operational tools?
  • Functional unit
  • Program office
  • Departments
  • Supervisor

Question No: 28 ( Marks: 1 ) - Please choose one
How many types of pricing reports are there?
  • 4
  • 6
  • 8
  • 10

Question No: 29 ( Marks: 1 ) - Please choose one
Which of the following have NO relative impact on price level?
  • Competitive prices
  • Customer budget
  • Bidder s cost estimate
  • Life-cycle cost

Question No: 30 ( Marks: 1 ) - Please choose one
Which of the following refers to how a product looks, feels, sounds, tastes, or smells?
  • Affordability
  • Conformance
  • Durability
  • Aesthetics

Question No: 31 ( Marks: 1 ) - Please choose one
Which of the following is referred to as the management section of quality management
by PMBOK?
  • Quality control
  • Quality assurance
  • Total quality control
  • Process control charts

Question No: 32 ( Marks: 1 ) - Please choose one
Which of the following is viewed as a vertical teamwork between managerial and non managerial
personnel?
  • Performance
  • Empowerment
  • Continuous improvement
  • Planning

Question No: 33 ( Marks: 1 ) - Please choose one
Empowerment, encourages which of the following?
  • Responsibility
  • Authority
  • Innovation
  • Motivation

Question No: 34 ( Marks: 1 ) - Please choose one
Which of the following means Quality related to price ?
  • Value
  • Quality control
  • Customer satisfaction
  • Price control

Question No: 35 ( Marks: 1 ) - Please choose one
The information provided by the Kano model, relates to which of the following?
  • Customer satisfaction
  • Value analysis
  • Quality control
  • Price control

Question No: 36 ( Marks: 1 ) - Please choose one
Process Analysis, is a function of which of the following?
  • Performance Analysis
  • Quality Metrics
  • Process Improvement Plan
  • Quality Improvement Plan

Question No: 37 ( Marks: 1 ) - Please choose one
How many tools are used for quality improvement?
  • Six
  • Seven
  • Eight
  • Nine

Question No: 38 ( Marks: 1 ) - Please choose one
What is the ratio of output to input called?
  • Efficiency
  • Effectiveness
  • Productivity
  • Quality

Question No: 39 ( Marks: 1 ) - Please choose one
Productivity, is an output input agreement on consideration of which of the following?
  • Quality and time
  • Competitiveness and time
  • Efficiency and time
  • Effectiveness and time

Question No: 40 ( Marks: 1 ) - Please choose one
Which of the following defines how & when various stakeholders receive information &
communicate with each other?
  • Site Waste Management Plan
  • Communication Management Plan
  • Chemicals Management Plan
  • Debt Management Plan

Question No: 41 ( Marks: 1 ) - Please choose one
Which of the following refers to the interpersonal influence modes that a project manager
can use?
  • Leadership style
  • Motivation style
  • Communication style
  • Controlling style

Question No: 42 ( Marks: 1 ) - Please choose one
The development of the overhead rates, is a function of how many separate elements?
  • Two
  • Three
  • Four
  • Five

Question No: 43 ( Marks: 3 )
For the construction of a network, how many inputs are required?

Question No: 44 ( Marks: 3 )
How can quality be achieved in a project?

Question No: 45 ( Marks: 3 )
What are the objectives of procurement planning?

Question No: 46 ( Marks: 5 )
What are the characteristics of effective communication?

Question No: 47 ( Marks: 5 )
Differentiate between preliminary project scope statement and detailed project
scope statement.

Question No: 48 ( Marks: 10 )
Discuss the method of preparing the schedules. Also explain its importance.

Question No: 49 ( Marks: 10 )
If a firm is using fixed price contract, how does it get advantage over others?
Reply


Possibly Related Threads…
Thread Author Replies Views Last Post
  All Unsolved Past Papers Final Term and Mid Term 2008 And 2009 viki 6 4,684 06-01-2012, 05:15 AM
Last Post: shahid11011
  CS402 Theory of Automata Mid Term Examination – Spring 2011 virtual university of pak Vuhelper 3 7,671 11-11-2011, 07:20 AM
Last Post: AliMustafa786
  cs301 final term current paper July 2011 Vuhelper 0 4,314 07-09-2011, 10:40 PM
Last Post: Vuhelper
  cs101 final term solve papers July 2011 Vuhelper 0 4,298 07-09-2011, 07:22 PM
Last Post: Vuhelper
  cs101 final term solve paper july 2011 Vuhelper 0 3,854 07-09-2011, 07:18 PM
Last Post: Vuhelper
  CS101- Introduction to Computing final term New paper July 2011 Vuhelper 0 3,508 07-09-2011, 07:04 PM
Last Post: Vuhelper
  CS101- Introduction to Computing final term paper July 2011 Vuhelper 0 3,482 07-09-2011, 07:02 PM
Last Post: Vuhelper
  CS101 Final term paper 2011 Subjective solved New Vuhelper 0 5,970 07-09-2011, 06:55 PM
Last Post: Vuhelper
  cS001 final term papers July 2011 Vuhelper 0 4,389 07-09-2011, 06:52 PM
Last Post: Vuhelper
  ACC501 Final Term July 2011 paper subjective Vuhelper 0 3,923 07-09-2011, 06:50 PM
Last Post: Vuhelper

Forum Jump:


Users browsing this thread: 1 Guest(s)