Q.
Let us assume that you are working as a Team lead in a renowned multinational company. The software project has 80 planned work tasks that are estimated to require 415 person-days to complete. At the time you have been asked to compute the Earned Value Analysis, 8 tasks have been completed. However, the project schedule indicates that 18 tasks should have been completed. The following scheduling data in person-days are available:
Task Planned Effort Actual Effort
1 3 3.5
2 4 5
3 5 5.5
4 4 3
5 6 7
6 7 6.5
7 5 5
8 7 7.5
9 8
10 8
11 3
12 2
13 14
14 2
15 7
16 6
17 8
18 7
Compute the following
1) SPI
2) Schedule variance
3) Percent scheduled for completion
4) Percent complete
5) CPI
6) Cost variance for the project.
Let us assume that you are working as a Team lead in a renowned multinational company. The software project has 80 planned work tasks that are estimated to require 415 person-days to complete. At the time you have been asked to compute the Earned Value Analysis, 8 tasks have been completed. However, the project schedule indicates that 18 tasks should have been completed. The following scheduling data in person-days are available:
Task Planned Effort Actual Effort
1 3 3.5
2 4 5
3 5 5.5
4 4 3
5 6 7
6 7 6.5
7 5 5
8 7 7.5
9 8
10 8
11 3
12 2
13 14
14 2
15 7
16 6
17 8
18 7
Compute the following
1) SPI
2) Schedule variance
3) Percent scheduled for completion
4) Percent complete
5) CPI
6) Cost variance for the project.
0300-9520262
Get solution in 24 hour |cpmputer & internet
mileys81:[SIZE="4"][SIZE="3"]....[/SIZE][/SIZE]